News
KYOWA PROJECT - PRECAST FENCE CONSTRUCTION PROGRESS
While the Global Covid-19 pandemic has been bringing crisis all over the world ,HRC Vietnam still work tirelessly, constantly providing our customers with the best PC products for each single project.
On 25/2/2020, HRC's Board of Directors had surveyed and checked the construction progress of Kyowa project.
The project has an area of 20,000m2, in Trang Due Industrial Park, Hai Phong.
This is a Japanese project with high technical and finishing requirements.
In this project, HRC is honored to participate in the construction of 3800m2 wall in all categories:
- 7-m boundary workshop wall, an area of 2400m2;
- Solid fence (250m long);
- Opening fence (300m long);
- Electrical room walls;
- Pump room walls;
- Garbage room wall;
Here are some images related to the category of solid fences and open fences:
1. Perspective drawings
2. Actual photos on site